[ARCHIVED] Carmichael Northbound Traffic to be Switched from Outside to Inside Lanes on Bridge Rehab Project

Wisconsin Department of Transportation Logo

Wisconsin Department of Transportation Logo


Traffic Advisory

Wisconsin Department of Transportation

Northwest Region ­ | 718 W. Clairemont Ave., WI 54701 | (715) 836-2399 | wisconsindot.gov

 

Release date: Tuesday, May 31, 2022

 

For more information, contact:

Christena T. O’Brien, WisDOT Northwest Region Communications Manager 
(715) 828-9471 or 
christena.obrien@dot.wi.gov

 

Northbound traffic to be switched from outside to inside lanes on bridge rehab project

Work on Carmichael Road structure in Hudson includes replacing expansion joints, making repairs  

 

Northbound traffic on the Carmichael Road bridge in the St. Croix County city of Hudson will be shifted from the outside to the inside lanes the afternoon of Wednesday, June 1, as the bridge rehabilitation project transitions to the next stage of construction.

Truck traffic should use Hanley Road to access WIS 35 if possible.

The Wisconsin Department of Transportation project involves:

  • Replacing the bridge's expansion joints.
  • Replacing the approach slabs on each side of the structure.
  • Patching cracks and spalling in the bridge girders and abutment wings.
  • Placing a polymer overlay on the bridge deck.
  • Adjusting and tensioning a tilted sign's anchor nuts.

 

Construction began May 2, and all but the polymer overlay is scheduled for completion in late August. 

For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s Northwest Region: