Posted on: June 7, 2021

[ARCHIVED] 2nd St/Hwy 35 Update 06/07

2nd St Hwy 25 Logo

This week:

  • Front Street to Coulee Road:
    • Grading for pavement replacement
    • Pouring concrete signal pole bases at Coulee Road
  • Coulee Road to Vine Street:
    • Concrete sidewalk and pavement at southwest corner of Locust Street and 2nd Street (Dunn Brothers’ Coffee corner)
    • Finish up any remaining restoration on west side of the street through downtown area
  • Vine Street to Lake Mallalieu:
    • Finish water and sanitary sewer service lines between Myrtle Street and St Croix Street
    • Storm sewer between Myrtle Street and St Croix Street
    • (Hopefully) begin water and sanitary sewer main work between St Croix Street and Division Street
  • North Hudson:
    • Water and sanitary sewer service lines between Monroe Street and Michaelson Street

 

Next week:

  • Front Street to Coulee Road:
    • Pour concrete pavement and/or curb in front of wastewater treatment plant
  • Coulee Road to Vine Street:
    • Begin lighting conduit work on east side of the street in the downtown area
  • Vine Street to Lake Mallalieu:
    • Water and/or sanitary sewer main replacement between St Croix Street and Division Street
    • Grading, curb, and sidewalk work between Myrtle Street and St Croix Street
  • North Hudson:
    • Finish water and sanitary sewer service lines between Monroe Street and Michaelson Street
    • Storm sewer between Monroe Street and Michaelson Street

 

Further out:

  • Work between Division Street and Lake Mallalieu - and related closures of the bridge to North Hudson - is still likely a few months away.
  • Work between Myrtle Street and Vine Street is likely at least 3 weeks away.


For more information, please see the document below:

Update 06/07/21 (PDF)