2nd St. and St. Croix.
*Work on the gate valves in 2nd St.
Buckeye St. – From 1st St to 2nd St.
*Fine grade the gravel in preparation for the asphalt base course.
Wisconsin St- From 11th St. to Prospect Park
*Remove and repair soft spots in the roadway.
Ward St.
*Work will start on the storm sewer structures.
*Concrete curb and gutter will be placed.