[ARCHIVED] 2nd St/Hwy 35 Update 06/14

2nd St Hwy 25 Logo

This week (week of 6/14):

  • Front Street to Coulee Road:
    • Prepare for restoration of the trail in front of the wastewater treatment plant
    • Set up the temporary pedestrian crossing movements at Coulee Road intersection traffic signal
    • Shift traffic over to the outside lanes, and begin pavement patching on inside lanes
  • Coulee Road to Vine Street:
    • Finish concrete work on west side of the street
  • Vine Street to Lake Mallalieu:
    • Water main construction between River Street and Division Street
    • Sanitary sewer main construction between St Croix Street and Division Street
    • Storm sewer construction between Myrtle Street and St Croix Street
    • Grading between Myrtle Street and St Croix Street
  • North Hudson:
    • Storm sewer between Monroe Street and Michaelson Street

Next week (week of 6/21):

  • Front Street to Coulee Road:
    • Paving trail in front of wastewater treatment plant
    • Pedestrian ramps at Coulee Road intersection
    • Work on Leverty Financial parking lot restoration
  • Coulee Road to Vine Street:
    • No work (see explanation below)
  • Vine Street to Lake Mallalieu:
    • Finish sanitary sewer between St Croix Street and Division Street
    • Begin water and sanitary sewer services between St Croix Street and Division Street
    • Finish grading between Myrtle Street and St Croix Street
    • Pour curb between Myrtle Street and St Croix Street
  • North Hudson:
    • Grading between Monroe Street and Michaelson Street