This week (week of June 1st):
- Front Street to Coulee Road:
- Grading for roadway pavement construction and restoration of the parking lot at Leverty Financial building
- Continue to work on concrete bases, wiring, pull boxes, etc. for a new signal at Coulee Road intersection
- Coulee Road to Vine Street:
- Complete concrete sidewalk work on the west side of the road with the exception of the southwest corner of the Locust Street intersection and the driveway to Riverfront Center
- Excavate and grade southwest corner of Locust Street intersection for concrete sidewalk installation
- Vine Street to Lake Mallalieu
- Construct water and sanitary sewer services between Myrtle Street and St Croix Street
- Construct storm sewer between Myrtle Street and St Croix Street, including at both intersections
- Potentially begin water and/or sanitary sewer main work between St Croix Street and Division Street
- North Hudson
- Continue with water and sanitary sewer services and storm sewer construction between Monroe Street and Michaelson Street
Next week (week of June 7th):
- Front Street to Coulee Road:
- Finish grading work
- Pour concrete curb and pavement near the wastewater treatment plant.
- Coulee Road to Vine Street:
- Finish southwest corner of Locust Street intersection
- Begin lighting work on the east side of the street
- Vine Street to Lake Mallalieu:
- Water and/or sanitary sewer mains from St Croix Street to Division Street
- Grading and potential curb and/or sidewalk work between Myrtle Street and Division Street
- North Hudson:
- Potentially begin water and/or sanitary sewer work between Michaelson Street and Sommers Street (to be determined based on conversations with the Village)
- Grading and potentially curb work between Monroe Street and Michaelson Street
For more information, please see the document below.
Update 06/02/21 (PDF)